Our Indicative project programme
Planning Application Preparation
Q1 2023 – Q1 2026
Public Consultation
Q1 2026
Planning Submission
Q1 or Q2 2026
Planning Determination Period
Q2-Q3 2026
Discharge of Conditions
Q3-Q4 2026
Ready to Build
Q1 2027. Construction and subsequent energisation to be determined post-completion of UK Grid Reform process. We will keep the community informed throughout and all information will be available here on the project website