INDICATIVE TIMELINE

Our Indicative project programme

Planning Application Preparation

Q1 2023 – Q2 2026

Public Consultation

Q1 2026

Planning Submission

Q2 / Q3 2026

Planning Determination Period

Q3 2026 - Q2 2027

Discharge of Conditions

Q2 2027 - Q4 2027

Ready to Build

Q1 2028. Construction and subsequent energisation to be determined post-completion of UK Grid Reform process. We will keep the community informed throughout and all information will be available here on the project website