INDICATIVE TIMELINE

Our Indicative project programme

Planning Application Preparation

Q1 2023 – Q1 2026

Public Consultation

Q1 2026

Planning Submission

Q1 or Q2 2026

Planning Determination Period

Q2-Q3 2026

Discharge of Conditions

Q3-Q4 2026

Ready to Build

Q1 2027. Construction and subsequent energisation to be determined post-completion of UK Grid Reform process. We will keep the community informed throughout and all information will be available here on the project website